Every client starts with a Build Report, so the numbers here are the same ones we took before anything was installed. We have no client case studies to show yet, and we are not going to borrow somebody else's. What we do have is what we measured on our own projects.

Our own books, first

A job that had been closed for months, rebuilt from scratch

We moved one finished project into a new system and rebuilt its cost from the source documents. The reported number and the real number were not the same, and nothing was broken. Some lines had never been labelled, so the reports had been counting them twice in opposite directions.

Reported cost$1,223,845.86
Real cost$876,373.85
Overstated by$347,472

This is the finding that decided what we sell. Not a system. The discipline that makes a system worth having.

One automated run

53 of 201 lines entering a budget priced at nothing

One run across three drawings on a residential project, before anyone signed anything. An incomplete budget looks exactly like a complete one: there is no red cell and no visible gap.

Quotable lines201
Entering at zero cost53
Uncatalogued value$112,329

Caught before the contract it is an adjustment. Caught afterwards it is a change order.

Reserved / first client build

No case study here yet.

Goes up with a name and numbers the builder will confirm.

Reserved / second client build

No case study here yet.

An empty slot is more credible than a stock photo or a claim nobody can check.

Your turn

Same measurements, run on your business

We test your enquiry form, time the reply and send the Build Report inside 24 hours. Free, yours to keep either way.